This page contains the latest information on construction activities on site, with key completed works to date and “Look Ahead” works. The newsletters are available to download in the “Documents” section of this website.
Look Ahead
Works Completed to Date
Structural builders work are ongoing.
Continuation of façade repairs and cleaning.
Removal of existing windows, starting on level 8.
Establishment of temporary mechanical & electrical services.
Scaffolding works ongoing.
Structural alteration works have commenced.
Completion of façade clean and repairs ongoing.
12 Week Look Ahead
Continuation of External Stone façade repairs & cleaning to all elevations.
Scaffolding works to Roof areas and existing stair cores to facilitate access for the works.
Removal of existing windows between lower Ground floor level and level 2
Installation of “New” windows to levels 2 down to lower ground level.
Structural alteration works to form “New lift” Cores at the North & South section of the building.
Structural builders work to form “New” Mechanical and Electrical Risers / Cupboards.
Blockwork to form “New” internal partitioning walls to all levels.
Installation of “New” Steel Roof structure at level 9
Removal of existing Basement floor to facilitate the installation of “New” Mechanical & Electrical plant locations.
Installation of “New” Rainwater system to all levels.
Construction of “New” drainage system in Basement.
Completion of the “New” UKPN Substation in the Basement